Florida Motion for Extension of Time: Rule 1.090(b)

Which rule governs depends on what you are asking the court to move.

KEY FLORIDA RULES

Key Florida rules for extending time

The rules that decide how, and whether, a deadline can be moved.

Authority
What it covers
Fla. R. Civ. P. 1.090(b)(1)
Extending time for good cause, before or after the deadline expires.
Fla. R. Civ. P. 1.090(b)(2)
Times the court may not extend, and the routes for case management orders and trial continuances.
Fla. R. Civ. P. 1.200(e) through (g)
Extensions of case management order deadlines, notices of unavailability, and inability to meet deadlines.
Fla. R. Civ. P. 1.201 and 1.460
Complex-case management orders and trial continuances.
Fla. R. Civ. P. 1.090(d) and 1.202(c)
Service of a motion and hearing notice, and conferral before filing.

Last reviewed November 19, 2026 against the rule text. General information for Florida practitioners, not legal advice. Rules change, so confirm against the current text and any local requirements before relying on it.

WHICH ROUTE APPLIES

Which route applies

Many Florida forms call this a motion for enlargement of time. The rule is Rule 1.090(b), titled "Extending Time," and it governs ordinary deadlines. Deadlines in a case management order and trial dates run through other rules, and some deadlines cannot be extended at all. Pick the wrong route and the motion fails on the standard before the court reaches your facts.

  • Ordinary deadline – A deadline set by a rule or court order: Rule 1.090(b)(1). Good cause. After the deadline has passed, also excusable neglect.
  • Case management order – A deadline in a case management order: Rule 1.200(e). Deadlines are strictly enforced unless the court changes them, and agreed orders are limited.
  • Complex-case order – A deadline in a complex-case management order: Rule 1.201. The complex-litigation procedures control.
  • Actual trial period – An actual trial period: Rule 1.460. Good cause, and continuances are disfavored.
  • No route – The time to move for new trial, rehearing, or to alter or amend a judgment; to move for relief under Rule 1.540(b); to appeal or petition for certiorari; or to move for a directed verdict. The court may not extend it (Rule 1.090(b)(2)).

The rule wording on this page is from the October 1, 2026 rulebook. Rule 1.090 was amended effective that date, so check older forms against the current text.

WHAT RULE 1.090(B) SAYS

What Rule 1.090(b) says

When an act must be done within a specified time, the court may, for good cause shown, extend the time in one of two ways. The rule treats the two moments differently.

  • Ask before the deadline – The court may extend with or without a motion or notice if the court acts, or a request is made, before the original time or its extension expires (Rule 1.090(b)(1)(A)). A request made before expiration is enough to qualify, so file it before the deadline passes, even if the hearing will come later.
  • After the deadline – On a motion made after the time has expired, the court may extend if the party failed to act because of excusable neglect (Rule 1.090(b)(1)(B)). Support the motion with an affidavit that says what happened, who was involved, when the problem was discovered, and what was done right away.
  • Fee motions – This standard is most often litigated with the 30-day deadline for motions for costs and attorneys' fees under Rule 1.525. Florida appellate courts have applied Rule 1.090(b) to that deadline. In Madill v. Rivercrest Community Ass'n, 273 So. 3d 1157 (Fla. 2d DCA 2019), the court reversed an order denying an enlargement for a late fee motion, where counsel moved as soon as the lapse was discovered, no prejudice was claimed, and there was no sign of bad faith. The case applied the rule's earlier lettering, Rule 1.090(b)(2).
  • Confer first – Rule 1.202 requires conferral before most non-dispositive motions. The only exemption that touches this subject is a motion for time to extend service of initial process, so a motion to extend any other deadline needs a certificate of conferral (Rule 1.202(c)).
  • Notice the hearing –A written motion that cannot be heard ex parte, and the notice of hearing, must be served a reasonable time before the hearing (Rule 1.090(d)). Compute dates under Rules 2.514 and 2.516.

CASE MANAGEMENT ORDER DEADLINES

Case management order deadlines

Rule 1.200(e) controls here, and it is stricter than Rule 1.090(b). See also our guide to reading a case management order.

  • Strictly enforced – Deadlines are strictly enforced unless changed by court order. The parties may submit an agreed order extending a deadline only if the extension does not affect their ability to meet the remaining dates in the order (Rule 1.200(e)(1)).
  • Amend rather than extend – If extending one deadline may affect a later one, the parties must seek an amendment of the case management order rather than move to extend the individual deadline (Rule 1.200(e)(1)).
  • What the motion must state – Any motion to extend a deadline or amend the order must state the basis and when it became known, whether the motion is opposed, the specific date requested and whether all parties agree to it, and the actions and dates that will let the movant meet the new deadline, including confirmed availability of required participants such as third-party witnesses or experts (Rule 1.200(e)(3)).
  • Notice of unavailability – A notice of unavailability has no effect on case management deadlines (Rule 1.200(f)).
  • If you cannot comply – A party who cannot meet the deadlines for any reason, including unavailable hearing time, may promptly set a case management conference and alert the court (Rule 1.200(g)).

FAQ

Frequently asked questions

Is a stipulation enough to extend a deadline?

For an ordinary deadline fixed by a court order, Rule 1.090(b) speaks of the court extending the time, so get an order. For case management order deadlines, the court may accept an agreed order if it does not affect the remaining dates (Rule 1.200(e)(1)).

Can I get more time to move for rehearing or for relief under Rule 1.540(b)?

No. Rule 1.090(b)(2) bars an extension of those times.

Does a notice of unavailability give me more time?

Not for case management order deadlines. Rule 1.200(f) says it has no effect on them.

Is a motion for enlargement of time different from a motion for extension of time?

No. The rule is titled "Extending Time"; older forms and the library use "enlargement."

Does this apply in probate and guardianship cases?

Rule 1.200 does not apply to an action or proceeding initiated under chapters 731 through 736, 738, and 744, Florida Statutes (Rule 1.200(a)(4)). The Florida Probate Rules have their own time provision, Rule 5.042, which its committee notes say is derived from Rule 1.090. Many probate and guardianship deadlines are set by statute, so read the statute before assuming a court can extend them.

See document automation in action

Start a 14-day free trial and generate your first Florida document today.

Start a free trial

Credit card required. Not charged during the trial. Cancel anytime before it ends.